The construction of major roads for L. Fonadhoo (phase 1) is well underway

The construction of major roads for L. Fonadhoo (phase 1) is well underway, with overall 88% project progress. We have completed construction of carriageway.
Project works involve construction of 27,848sqm asphalt roads, stormwater management system, speed breakers and road markings on 10,205m. The value of the project is MVR 25.5 million.