Work on Design and Build of N. Landhoo Harbour is well underway

Work on Design and Build of N. Landhoo Harbour is well underway, with overall 70% project progress. We have completed installation of harbor pavement and commenced construction of breakwater on 9th October 2021.
Scope of works for the project include dredging and excavation operations of 25,000cbm; the construction of a 256m quay wall; a 401m breakwater; and a 60m revetment. Additionally, the installation of navigation lights, streetlights, and installation of 1,280sqm of paved area will also be undertaken. The value of the project is MVR 35.60 million.