30 Apr Design and Build of Sh. Lhaimagu Harbour is well underway. The quay wall concrete block installation works of the project are ongoing, with 59% completion. Quay wall concrete works are also currently ongoing.
Design and Build of Sh. Lhaimagu Harbour is well underway. The quay wall concrete block installation works of the project are ongoing, with 59% completion. Quay wall concrete works are also currently ongoing.
Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of a 350m breakwater; a 276m quay wall; a 500m revetment; installation of 1,380sqm pavement, installation of navigation lights and streetlights. The value of the project is MVR 53.1 million.