Work on design and build of Sh. Bilehfahi Harbor is well underway

Work on design and build of Sh. Bilehfahi Harbor is well underway, with overall 53% project progress. We have completed construction of quay wall for Sh. Bilehfahi Harbor on 30th October 2021. Installation of harbor pavement is currently ongoing.
Scope of works involve, dredging and excavation operations of 24,125cbm; construction of a 376m breakwater; a 98m quay wall; installation of 1,150 sqm paved area and installation of streetlights. The value of the project is MVR 28.42 million.