We have completed installation of blocks for quay wall construction of Lh. Hinnvaru Harbor. The concrete works of quay wall are currently ongoing, with 57% completion.
Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment. The value of the project is MVR 99.52 million.