Completion of 75% of the storm water network installation works and 64% of ABC laying works needed for B. Eydhafushi road construction project

75% of storm water network installation works and 64% of ABC laying works needed for B. Eydhafushi road construction project are now complete. All asphalt materials needed to finish the project have also been delivered to the project site.
The project includes developing all main roads of Eydhafushi, detailed surveys of existing sidewalks and curbstones, design of asphalt pavements and a stormwater management system with gravity pipe networks to prevent flooding of roads for a clean and safe environment.
The MVR 38.3 million road construction project was awarded to us on 1st April 2019 was subsequently mobilized on 22nd April 2019. Overall progress of the project is 79%.