We have completed the construction of AA. Himandhoo harbour on 20th April 2020

We have completed the construction of AA. Himandhoo harbour on 20th April 2020. The project, awarded to us in March 2019, was subsequently mobilized in April 2019.
Project work includes 28,030 cbm of dredging and excavation and construction of a 372 m quay wall. The construction of a 405 m breakwater; a 141 m revetment: a bridge; a ramp and a 3 m width concrete jetty were also undertaken.