We have completed installation of precast concrete blocks required for the quay wall construction of N. Landhoo Harbor

We have completed installation of precast concrete blocks required for the quay wall construction of N. Landhoo Harbor on 6th May 2021.
Scope of works for the project include dredging and excavation operations of 25,000cbm; the construction of a 256m quay wall; a 401m breakwater; and a 60m revetment. Additionally, the installation of navigation lights, streetlight and installation of 1,280sqm of paved area will also be undertaken. The value of the project is MVR 32.4 million.
No Comments

Sorry, the comment form is closed at this time.