Work on the design and build of Aa. Ukulhas Harbor Quay Wall and Jetty Construction is well underway

Work on the design and build of Aa. Ukulhas Harbor Quay Wall and Jetty Construction is well underway, with overall 84% project progress. We have completed installation of harbor pavement.
The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m jetty and installation of 580sqm harbor pavement. The value of the project is MVR 19.9 million.