We have commenced physical works of Sh. Narudhoo Harbor Development Project

We have commenced physical works of Sh. Narudhoo Harbor Development Project on 4th May 2023. New harbor basin dredging operations are currently ongoing.
Scope of works include, 51,212cbm of harbor dredging operations, 4,120cbm of channel dredging operations, construction of 371m breakwater; a 205m revetment; a 210m quay wall; installation of 955sqm harbor pavement, construction of a ramp and installation of harbor lights.