Work on B. Fulhadhoo Harbour is well underway

Work on B. Fulhadhoo Harbour is well underway, with overall 50% project progress. Dredging works for the project are currently ongoing, with 93% completion.

The B. Fulhadhoo Harbour project consists of channel dredging of 29,167.50cbm; harbour basin dredging of 22,694cbm; construction of a 108m breakwater; a 302m revetment; a 223m quay wall; 558sqm of paved area and installation of navigation lights. The estimated value of the project is MVR 48.29 million. The project was mobilized on 10th November 2019.