23 Sep Work on Design and Build of R. Rasmaadhoo Harbour is underway
Work on Design and Build of R. Rasmaadhoo Harbour is underway, with overall 11% project progress Dredging works for the project is currently ongoing, with 10% completion.
Project works consists of; dredging and excavation operations of 9,000cbm; construction of a 377m breakwater; 600sqm of paved area and installation of navigation lights and streetlights. The estimated value of the project is MVR 21.91 million. The project was awarded on 10th December 2019.
Sorry, the comment form is closed at this time.