10 Aug Dredging works for S. Hulhudhoo Harbour is Well Underway
Dredging works for S. Hulhudhoo Harbour is well underway, with project mobilization on 28th July 2020.
The S. Hulhudhoo harbor development scheme consist of dredging & excavation operations of 88,623cbm, breakwater construction of 114m, revetment construction of 624m, quay wall construction of 742m, bridge construction of 9m x 4m, installation of 2,250 sqm pavement, installation of navigation aids, streetlights and ramp construction. The estimated value of the project is MVR 61.4 million.
Sorry, the comment form is closed at this time.