15 Mar Work on design and build of Adh. Hangnaameedhoo Harbor Development Project is well underway
Work on design and build of Adh. Hangnaameedhoo Harbor Development Project is well underway, with overall 72% project progress. Fifth shipment of precast concrete blocks required for quay wall construction have been delivered to the project site on 13 Mar 2022.
The Adh. Hangnaameedhoo Harbour project consists of; dredging and excavation operations of 6,363.1cbm; construction of a 204m breakwater; a 266m quay wall; a 160m revetment; installation of 1,330sqm of paved area and installation of streetlights. The value of the project is MVR 29.1 million.