The casting works & installation of electrical junction box & pipe laying works for Ha. Hoarafushi Road Construction Project are ongoing at 83% & 36% completion respectively.

The casting works & installation of electrical junction box & pipe laying works for Ha. Hoarafushi Road Construction Project are ongoing at 83% & 36% completion respectively. Additionally, curbstone installation works are now ongoing.
The scope of the project includes, construction of 11 roads measuring 5.3km in length, construction of a 25,909 sqm carriageway, installation of 11,114sqm pavement, installation of stormwater infiltration system, streetlights and road markings. The value of the project is MVR 71.90 million.