02 Sep Work on Hdh. Hanimaadhoo Harbour is well underway
Work on Hdh. Hanimaadhoo Harbour is well underway, with overall 20% project progress. Dredging works for the project is currently ongoing, with 43% completion.
The Hdh. Hanimaadhoo Harbour project consists of; harbour basin dredging of 53,523cbm; maintenance dredging of 31,576cbm; construction of a 355m breakwater; a 50m revetment; a 270m quay wall; 2,583sqm of paved area and installation of navigation lights. The estimated value of the project is MVR 57.12 million. The project was mobilized on 05 May 2020.