11 Apr 2020 - 14:00 The construction of AA. Himandhoo harbour is nearing completion
The construction of AA. Himandhoo harbour is nearing completion, with 94% project progress.
Current work involves construction of a breakwater with backfill; construction of a 3m width concrete jetty; revetment works and mooring buoy installation.
The project, which was awarded in April 2019, is expected to be completed in April 2020.