01 Feb Work on design and build of R. Rasmaadhoo Harbor is well underway
Work on design and build of R. Rasmaadhoo Harbor is well underway, with overall 80% project progress. We have completed installation of precast concrete blocks required for quay wall construction on 29 Jan 2022. Construction of breakwater and installation of harbor pavement is currently ongoing, with 82% and 69% completion respectively.
Project works consists of; dredging and excavation operations of 8,100cbm; construction of a 377m breakwater, installation of 600sqm of paved area, installation of navigation lights and streetlights. The value of the project is MVR 28.1 million.