04 Jun R. Ungoofaaru Road Construction Project (phase 2) is well underway.
Posted at 15:52h
in
News
by Samahath Zuhuree
R. Ungoofaaru Road Construction Project (phase 2) is well underway. Sidewalk paving works are ongoing with 98% completion. We have commenced ABC laying works.
Scope of works include, a 7511.70sqm of carriageway (subgrade, subbase, asphalt), a 2291.75sqm of sidewalk pavement, installation of stormwater management system, road makings and streetlights. The value of the project is MVR 20.42 million.