21 Jun We have completed quay wall concrete works for Lh. Hinnavaru Harbor Extension Project.
We have completed quay wall concrete works for Lh. Hinnavaru Harbor Extension Project. Harbor pavement casting works are currently ongoing.
Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a 123.9m breakwater; a 170.55m revetment. The value of the project is MVR 99.52 million.