Work on K. Thilafushi Waste Area Rehabilitation project is well underway, with overall 10% project progress. Installation of a surface water management system and works on a carriageway is currently ongoing, with 30% and 15% completion, respectively.
The K. Thilafushi Waste Area Rehabilitation project consists of; administrative building for civil and steel works; shed for waste storage area; heavy vehicle parking shed, workshop building and a fuel tank station. The estimated value of the project is USD 8.8 million. The project was mobilized on 15 February 2020.