13 Feb Work on design and build of Hdh. Hanimaadhoo Harbor Development Project is well underway
Work on design and build of Hdh. Hanimaadhoo Harbor Development Project is well underway, with overall 55% project progress. Quay wall concrete works are ongoing. We have commenced sand-filled breakwater construction works.
The Hdh. Hanimaadhoo Harbour project consists of; new harbor basin dredging of 53,522.50cbm; harbor entrance channel dredging of 31,575.50cbm; construction of a 355m breakwater; a 50m revetment; a 270m quay wall and installation of 2,583sqm of paved area. The value of the project is MVR 64.6 million.
Sorry, the comment form is closed at this time.