30 May Gn. Fuvahmulah Internal Roads Construction Project is currently ongoing with overall 86% project progress.
The Gn. Fuvahmulah Internal Roads Construction Project is currently ongoing with overall 86% project progress. Sub-base work has reached 92% completion, and sub grade work has reached 66% completion. Asphalt laying work and installation of streetlights is currently ongoing at the site.
Scope of works for the project include sub base preparation of 122,659sqm; an asphalt wearing course of 95, 239 sqm; footpath preparation of 27,450sqm; road marking, streetlights, and storm water drainage works of 19,940m. The value of the project is MVR 302.72 million.
#MTCCProjects #RayyithungeKunfuni
Sorry, the comment form is closed at this time.