26 Jun Second shipment of rock boulders required for N. Velidhoo Boat Beaching Area project have been delivered to the project site.
Second shipment of rock boulders required for N. Velidhoo Boat Beaching Area project have been delivered to the project site. 85% of the reclamation works have been completed. Revetment works are currently ongoing with 58% completion.