Work on Ha. Ihavandhoo Harbour development project is underway, with overall 22% project progress. Harbour dredging operations are currently ongoing with 46% completion.

The harbor development scheme consists of dredging and reclamation operations of 21,295cbm; breakwater construction of 284m; quay wall construction of 95m; and revetment construction of 178m. It also involves the installation of 4,582sqm of pavement; installation of navigation lights; streetlights and ramp construction. The estimated value of the project is MVR 51.72 million. The project was awarded to us on 26th August 2019.