The construction of major roads for L. Fonadhoo is well underway

The construction of major roads for L. Fonadhoo is well underway, with overall 69% project progress. ABC laying works for the project is currently ongoing. The machinery required for the carriageway have also been delivered to the project site.
Project works involve construction of 27,848sqm asphalt roads, stormwater management system, speed breakers and road markings on 13,702m. The road development project was contracted to us by Ministry of National Planning, Housing and Infrastructure and was mobilized on 26th June 2019. The project is valued at MVR. 25.5 million.
No Comments

Sorry, the comment form is closed at this time.