The construction of Bahaudheen Road at S. Hulhumeedhoo is nearing completion

The construction of Bahaudheen Road at S. Hulhumeedhoo is nearing completion, with overall 97% project progress. The installation of stormwater pump station is currently ongoing with 83% completion.
Scope of works involve sidewalks of 6,060sqm; a carriageway of 17,776sqm, installation of a stormwater management system; streetlights and road markings. The project is valued at MVR. 41.8 million.