Construction of Major Roads at R. Dhuvaafaru (2nd phase) is well underway

Construction of Major Roads at R. Dhuvaafaru (2nd phase) is well underway, with overall 65% project progress. We have completed subbase and subgrade works of carriageway and installation of stormwater infiltration system. Sidewalk pavements works are ongoing, with 65% completion.
Scope of works involve, construction of 9 roads with a total length of 17,790sqm; sidewalks of 6,923sqm; a carriageway of 17,790sqm; installation of stormwater management system, road lighting and road markings. The project is valued at MVR 37.8 million.