New harbor basin dredging operations for Ha. Dhidhoo Harbor Extension and Jetty Construction Project is currently ongoing. Project works involve, dredging and excavation operations of 78,000cbm; construction of a 616m breakwater; a 185m revetment; a 326m quay wall; installation of 4,320sqm harbor pavement and installation of...

The first shipment of precast concrete blocks required for quay wall construction of Hdh. Hanimaadhoo Harbor have been delivered to project site on 17th Nov 2021. Existing harbor quay wall repair work is currently ongoing. The Hdh. Hanimaadhoo Harbour project consists of; new harbor basin dredging...

The second shipment of rock boulders required for breakwater construction of Sh. Feydhoo Harbor have been delivered to the project site. The Sh. Feydhoo Harbour project consists of; dredging and excavation operations of 27,500cbm; construction of a 378m breakwater; a 90m revetment; a 276m quay wall;...

The fourth shipment of rock boulders required for the construction of revetment at M. Dhiggaru have been delivered to the project site on 23rd October 2021. Scope of works for the project include; reclamation operations of 25 hectares; construction of a 384m rock boulder revetment and...

MTCC has signed with Ministry of National Planning, Housing and Infrastructure  towards implementing the design and build of Gdh.Madaveli-Hoadehdhoo Causeway Construction Project. COO Shahid Hussain Moosa signed on behalf of MTCC and Permanent Secretary Ms. Zeeniya Hameed signed on behalf of the MNPHI. MP Hussain...

We have commenced physical works of N. Manadhoo Harbor Channel Dredging and Breakwater Construction Project on 24th October 2021. Scope of works for the project include; dredging and excavation operations of 29,038cbm; construction of a 195m breakwater; a 188m revetment; a concrete bridge; a ramp, and...

We have completed K. Guraidhoo Picnic Island Reclamation and Shore Protection Project on 11th September 2021. The K. Guraidhoo Picnic Island Reclamation and Shore Protection Project consists of reclamation operations of 1.7 hectares, 278m rock boulder revetment construction and 160m rock boulder groyne construction. The value...

The first shipment of rock boulders required for shore protection works of Ga. Dhaandhoo have been delivered to the project site on 9th October 2021. The Ga. Dhaandhoo Land Reclamation and Shore Protection project consists of; dredging and reclamation operations of 25 hectares; construction of a...

The first shipment of rock boulders required for the breakwater construction of Sh. Bilehfahi Harbor have been delivered to the project site on 28th September 2021. Scope of works involve, dredging and excavation operations of 24,125cbm; construction of a 376m breakwater; a 98m quay wall; installation...

We have completed installation of precast concrete blocks and capping beam works required for the construction of quay wall of Lh. Hinnavaru Harbor. The installation of harbor pavement is currently ongoing. Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of...

The fourth shipment of precast concrete blocks required for the construction of quay wall of S. Hulhudhoo Harbor have been delivered to the project site on 21st September 2021. The installation of precast concrete blocks required for the quay wall is currently ongoing, with 56%...

The second shipment of rock boulders required for Ha. Hoarafushi Airport Shore Protection Project have been delivered to the project site on 19th September 2021. Scope of works for the project include; coastal protection and construction of a concrete culvert on the causeway which connects from...

The construction of Bahaudheen Road at S. Hulhumeedhoo is nearing completion, with overall 97% project progress. The installation of stormwater pump station is currently ongoing with 83% completion. Scope of works involve sidewalks of 6,060sqm; a carriageway of 17,776sqm, installation of a stormwater management system; streetlights...

The rock boulders required for the construction of groyne for Hdh. Hanimaadhoo Harbour have been delivered to the project site on 14th September 2021. The Hdh. Hanimaadhoo Harbour project consists of; new harbor basin dredging of 53,522.50cbm; harbor entrance channel dredging of 31,575.50cbm; construction of a...

The second shipment of rock boulders required for breakwater construction for V. Fulidhoo coastal protection project have been delivered to the project site. Scope of the project include, dredging, backfilling and beach filling of 12,127.50cbm of sand; construction of a 210m groynes and 270m breakwater. The...

The second shipment of rock boulders required for the breakwater construction of Adh. Hangnaameedhoo Harbor have been delivered to the project site on 4th September 2021. We have completed new harbor basin and channel dredging operations. The Adh. Hangnaameedhoo Harbour project consists of; dredging and excavation...

New harbor basin dredging and entrance channel dredging operations to a depth of 8.5MSL (Mean Sea Level) is currently ongoing for S. Hulhumeedhoo MIFCO Harbor Development Project. Our “Jarraafaa 3” runs 24 hrs in these operations in 2 shifts. Scope of works include; dredging and excavation...

The first shipment of rock boulders required for the breakwater construction of Sh. Feydhoo Harbor have been delivered to the project site on 4th September 2021. New harbor basin dredging operations for the project is currently ongoing, with 97% completion. The Sh. Feydhoo Harbour project consists...

The final shipment of precast concrete blocks required for the construction of quay wall of Sh. Bilehfahi Harbor have been delivered to the project site on 30th August 2021. Scope of works involve, dredging and excavation operations of 24,125cbm; construction of a 376m breakwater; a 98m...

The second shipment of rock boulders required for the quay wall construction of S. Hithadhoo Old Harbor have been delivered to the project site on 29th August 2021. The S. Hithadhoo Old Harbour Project consists of; dredging and excavation operations of 234,297cbm; construction of a 800m...

We have commenced installation of precast concrete blocks required for the quay wall construction of S. Hithadhoo Old Harbor on 17th August 2021. The S. Hithadhoo Old Harbour Project consists of; dredging and excavation operations of 234,297cbm; construction of a 800m breakwater; a 284m quay wall;...

The second shipment of rock boulders required for the construction of quay wall of Sh. Bilehfahi Harbor have been delivered to the project site on 10th August 2021. Scope of works involve, dredging and excavation operations of 24,125cbm; construction of a 376m breakwater; a 98m quay...

We have commenced installation of precast concrete blocks required for the construction of quay wall of Lh. Hinnavaru Harbor on 11th July 2021. Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a...

The 2nd shipment of rock boulders required for breakwater construction of N. Miladhoo Harbor have been delivered to the project site on 8th July 2021. The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment;...

Sheet piling for the construction of the quay wall of K. Dhoonidhoo Harbor Redevelopment and Reclamation Project is currently ongoing, with 85% project progress. The K. Dhoonidhoo Harbour Redevelopment and Reclamation project consists of; dredging and excavation operations of 4.61acre; reclamation of 3.75 acre; construction of...

New harbor basin dredging works for the Sh. Lhaimagu Harbor development project is currently ongoing, with 88% completion. The Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of a 350m breakwater; a 276m quay wall; a 500m revetment; installation of 1,380sqm...

We have commenced construction of breakwater of Adh. Hangnaameedhoo Harbor. The dredging operations of boat beaching area are currently progressing. The Adh. Hangnaameedhoo Harbour project consists of; dredging and excavation operations of 6,363.1cbm; construction of a 204m breakwater; a 266m quay wall; a 160m revetment; installation...

The construction of OPD building of Gdh. Thinadhoo Dr. Abdul Samad Memorial Hospital development project is currently ongoing, with 71% completion. We have completed concrete, masonry and roofing works of both OPD building and Labor Wing building. Scope of project works include construction of the OPD...

We have commenced installation of precast concrete blocks required for the construction of quay wall of Aa. Ukulhas Harbor on 26th June 2021. The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m...

First shipment of rock boulders required for V. Fulidhoo Shore Protection Project have been delivered to the project site. Scope of the project include, dredging, backfilling and beach filling of 12,127.50cbm of sand; construction of a 210m groynes and 270m breakwater. The value of the project...

New harbor basin dredging operations and breakwater construction for N. Miladhoo Harbor Project are currently ongoing, with 91% and 75% completion respectively. The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment; a 286m quay...

The second shipment of precast concrete blocks required for the construction of quay wall of Ha. Ihavandhoo Harbor have been delivered to the project site. Scope of works for the project include dredging and excavation operations of 30,509cbm; the construction of a 95m quay wall; a...

We have completed maintenance dredging works of Aa. Ukulhas Harbor quay wall and jetty construction project. The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m jetty and installation of 580sqm harbor pavement....

We have completed the installation of precast concrete blocks required for the construction of the quay wall of R. Maduvvari South Harbor today. The R. Maduvvari South Harbor development scheme consists of dredging 7,280cbm from channel, dredging 65,520cbm from harbor basin, breakwater construction of 411m, quay...

The second barge of rock boulders required for Hdh. Hanimaadhoo Harbor project have been delivered to the project site on 7th June 2021. The Hdh. Hanimaadhoo Harbour project consists of; new harbor basin dredging of 53,522.50cbm; harbor entrance channel dredging of 31,575.50cbm; construction of a 355m...

The first shipment of rock boulders required for the breakwater construction of Adh. Hangnaameedhoo Harbor have been delivered to the project site on 31st May 2021. The Adh. Hangnaameedhoo Harbour project consists of; dredging and excavation operations of 6,363.1cbm; construction of a 204m breakwater; a 266m...

We have completed 60% of reclamation works for R. Dhuvaafaru Land Reclamation and Shore Protection Project. The R. Dhuvaafaru Land Reclamation and Shore Protection project consists of dredging and reclamation operations of 22.2 hectares; 423m rock boulder revetment construction and 70m breakwater construction. [foogallery id="22646"] ...

The second shipment of rock boulders required for the breakwater construction of Dh. Hulhudheli Harbor have been delivered to the project site on 17th May 2021. Scope of works for the project include dredging and excavation operations of 49,612 cbm; the construction of a 432m quay...

The 2nd shipment of rock boulders required for breakwater construction of N. Miladhoo Harbor have been delivered to the project site on 24th April 2021. The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment;...

The pre-cast concrete blocks required for quay wall construction of R. Angolhitheem Harbour have been delivered to the project site on 12th April 2021. We have scheduled to commence the installation of pre-cast concrete blocks during this month. The R. Angolhitheem Harbour project consists of; dredging...

First shipment of rock boulders required for breakwater construction of Sh. Foakaidhoo Harbor have been delivered to the project site on 24th March 2021. Dredging works for the new harbor basin is progressing well with 58% completion. The Sh. Foakiadhoo Harbour project consists of; new harbor...

#TeamMTCC held an event today, to mark the commencement of physical works of the construction of an accessible ramp in artificial beach for the differently abled community. CEO Adam Azim, Minister of Youth, Sport and Community Empowerment Ahmed Mahloof and members of Maldives Association for...

First shipment of rock boulders required for breakwater construction of Dh. Hulhudheli Harbor have been delivered to the project site on 18th March 2021. We have completed new harbor basin dredging works. Scope of works for the project include dredging and excavation operations of 49,612 cbm;...

Highlights of the survey team visit to Ha. Thuraakunu, Ha. Uligan, Ha. Molhadhoo, Ha. Ihavandhoo, Ha. Maarandhoo, Ha. Thakandhoo Ha. Dhihdhoo and Ha. Vashafaru for preparations towards implementing Phase 1 of the "Integrated National Public Ferry Network Project". The objective of this project is to connect...

With the arrival of Mahaa Jarraafu, land reclamation works at R. Dhuvaafaru will commence soon. The R. Dhuvaafaru Land Reclamation and Shore Protection project consists of dredging and reclamation operations of 22.2 hectares; 423m rock boulder revetment construction and 70m breakwater construction. [foogallery id="21361"] ...

We have commenced physical works of K. Himmafushi Harbor Development (phase 2) project. The scope of the project includes, dredging and excavation operations of 28,760cbm; construction of a 38m breakwater; a 287m revetment; a 172m quay wall; installation of 772sqm harbor pavement; navigation lights and streetlights. [foogallery...

We have commenced maintenance dredging works of Aa. Ukulhas Harbor quay wall and jetty construction project. The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m jetty and installation of 580sqm harbor pavement....

We have started physical works of R. Dhuvaafaru land reclamation and shore protection project. The R. Dhuvaafaru Land Reclamation and Shore Protection project consists of dredging and reclamation operations of 22.2 hectares; 423m rock boulder revetment construction and 70m breakwater construction. [foogallery id="20968"] ...

MTCC has signed with Ministry of National Planning, Housing and Infrastructure  towards implementing the service agreement of the 1st phase of the "Integrated National Public Ferry Network Project" today. COO Shahid Hussain Moosa signed on behalf of MTCC and Mr. Mohamed Imad, Director General, signed...

MTCC has signed with Ministry of National Planning, Housing and Infrastructure  towards implementing Reclamation and Harbor Development at Lh. Felivaru today. CEO Adam Azim signed on behalf of MTCC and Ms. Fathimath Shaana Farooq, Director General, signed on behalf of MNPHI. Scope of the project includes, dredging...

MTCC has signed with Ministry of National Planning, Housing and Infrastructure  towards implementing the 1st phase of the "Integrated National Public Ferry Network Project" today. CEO Adam Azim signed on behalf of MTCC and Ms. Fathimath Shaana Farooq, Director General, signed on behalf of MNPHI. The...