We have commenced installation of precast concrete blocks required for the quay wall construction of S. Hithadhoo Old Harbor on 17th August 2021. The S. Hithadhoo Old Harbour Project consists of; dredging and excavation operations of 234,297cbm; construction of a 800m breakwater; a 284m quay wall;...

The second shipment of rock boulders required for the construction of quay wall of Sh. Bilehfahi Harbor have been delivered to the project site on 10th August 2021. Scope of works involve, dredging and excavation operations of 24,125cbm; construction of a 376m breakwater; a 98m quay...

We have commenced installation of precast concrete blocks required for the construction of quay wall of Lh. Hinnavaru Harbor on 11th July 2021. Scope of works for the project include, reclamation operations of 3.2 hectare; dredging operations of 65,170.76cbm; construction of a 421m quay wall; a...

The 2nd shipment of rock boulders required for breakwater construction of N. Miladhoo Harbor have been delivered to the project site on 8th July 2021. The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment;...

Sheet piling for the construction of the quay wall of K. Dhoonidhoo Harbor Redevelopment and Reclamation Project is currently ongoing, with 85% project progress. The K. Dhoonidhoo Harbour Redevelopment and Reclamation project consists of; dredging and excavation operations of 4.61acre; reclamation of 3.75 acre; construction of...

New harbor basin dredging works for the Sh. Lhaimagu Harbor development project is currently ongoing, with 88% completion. The Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of a 350m breakwater; a 276m quay wall; a 500m revetment; installation of 1,380sqm...

We have commenced construction of breakwater of Adh. Hangnaameedhoo Harbor. The dredging operations of boat beaching area are currently progressing. The Adh. Hangnaameedhoo Harbour project consists of; dredging and excavation operations of 6,363.1cbm; construction of a 204m breakwater; a 266m quay wall; a 160m revetment; installation...

The construction of OPD building of Gdh. Thinadhoo Dr. Abdul Samad Memorial Hospital development project is currently ongoing, with 71% completion. We have completed concrete, masonry and roofing works of both OPD building and Labor Wing building. Scope of project works include construction of the OPD...

We have commenced installation of precast concrete blocks required for the construction of quay wall of Aa. Ukulhas Harbor on 26th June 2021. The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m...

First shipment of rock boulders required for V. Fulidhoo Shore Protection Project have been delivered to the project site. Scope of the project include, dredging, backfilling and beach filling of 12,127.50cbm of sand; construction of a 210m groynes and 270m breakwater. The value of the project...

New harbor basin dredging operations and breakwater construction for N. Miladhoo Harbor Project are currently ongoing, with 91% and 75% completion respectively. The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment; a 286m quay...

The second shipment of precast concrete blocks required for the construction of quay wall of Ha. Ihavandhoo Harbor have been delivered to the project site. Scope of works for the project include dredging and excavation operations of 30,509cbm; the construction of a 95m quay wall; a...

We have completed maintenance dredging works of Aa. Ukulhas Harbor quay wall and jetty construction project. The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m jetty and installation of 580sqm harbor pavement....

We have completed the installation of precast concrete blocks required for the construction of the quay wall of R. Maduvvari South Harbor today. The R. Maduvvari South Harbor development scheme consists of dredging 7,280cbm from channel, dredging 65,520cbm from harbor basin, breakwater construction of 411m, quay...

The second barge of rock boulders required for Hdh. Hanimaadhoo Harbor project have been delivered to the project site on 7th June 2021. The Hdh. Hanimaadhoo Harbour project consists of; new harbor basin dredging of 53,522.50cbm; harbor entrance channel dredging of 31,575.50cbm; construction of a 355m...

The first shipment of rock boulders required for the breakwater construction of Adh. Hangnaameedhoo Harbor have been delivered to the project site on 31st May 2021. The Adh. Hangnaameedhoo Harbour project consists of; dredging and excavation operations of 6,363.1cbm; construction of a 204m breakwater; a 266m...

We have completed 60% of reclamation works for R. Dhuvaafaru Land Reclamation and Shore Protection Project. The R. Dhuvaafaru Land Reclamation and Shore Protection project consists of dredging and reclamation operations of 22.2 hectares; 423m rock boulder revetment construction and 70m breakwater construction. [foogallery id="22646"] ...

The second shipment of rock boulders required for the breakwater construction of Dh. Hulhudheli Harbor have been delivered to the project site on 17th May 2021. Scope of works for the project include dredging and excavation operations of 49,612 cbm; the construction of a 432m quay...

The 2nd shipment of rock boulders required for breakwater construction of N. Miladhoo Harbor have been delivered to the project site on 24th April 2021. The N. Miladhoo Harbour project consists of; dredging and excavation operations of 37,222cbm; construction of a 248m breakwater; a 137m revetment;...

The pre-cast concrete blocks required for quay wall construction of R. Angolhitheem Harbour have been delivered to the project site on 12th April 2021. We have scheduled to commence the installation of pre-cast concrete blocks during this month. The R. Angolhitheem Harbour project consists of; dredging...

First shipment of rock boulders required for breakwater construction of Sh. Foakaidhoo Harbor have been delivered to the project site on 24th March 2021. Dredging works for the new harbor basin is progressing well with 58% completion. The Sh. Foakiadhoo Harbour project consists of; new harbor...

#TeamMTCC held an event today, to mark the commencement of physical works of the construction of an accessible ramp in artificial beach for the differently abled community. CEO Adam Azim, Minister of Youth, Sport and Community Empowerment Ahmed Mahloof and members of Maldives Association for...

First shipment of rock boulders required for breakwater construction of Dh. Hulhudheli Harbor have been delivered to the project site on 18th March 2021. We have completed new harbor basin dredging works. Scope of works for the project include dredging and excavation operations of 49,612 cbm;...

Highlights of the survey team visit to Ha. Thuraakunu, Ha. Uligan, Ha. Molhadhoo, Ha. Ihavandhoo, Ha. Maarandhoo, Ha. Thakandhoo Ha. Dhihdhoo and Ha. Vashafaru for preparations towards implementing Phase 1 of the "Integrated National Public Ferry Network Project". The objective of this project is to connect...

With the arrival of Mahaa Jarraafu, land reclamation works at R. Dhuvaafaru will commence soon. The R. Dhuvaafaru Land Reclamation and Shore Protection project consists of dredging and reclamation operations of 22.2 hectares; 423m rock boulder revetment construction and 70m breakwater construction. [foogallery id="21361"] ...

We have commenced physical works of K. Himmafushi Harbor Development (phase 2) project. The scope of the project includes, dredging and excavation operations of 28,760cbm; construction of a 38m breakwater; a 287m revetment; a 172m quay wall; installation of 772sqm harbor pavement; navigation lights and streetlights. [foogallery...

We have commenced maintenance dredging works of Aa. Ukulhas Harbor quay wall and jetty construction project. The scope of the project includes, dredging and excavation operations of 19,630cbm; construction of a 31m breakwater; a 136m quay wall; a 138.73m jetty and installation of 580sqm harbor pavement....

We have started physical works of R. Dhuvaafaru land reclamation and shore protection project. The R. Dhuvaafaru Land Reclamation and Shore Protection project consists of dredging and reclamation operations of 22.2 hectares; 423m rock boulder revetment construction and 70m breakwater construction. [foogallery id="20968"] ...