Laying of Aggregate Base Course (ABC layer) and pavement works for R. Dhuvaafaru road construction project are underway, with 38% project progress.The ABC layer which is placed on top of the Sub-Grade provides a stable foundation and increases the durability of roads. The project, which was...

‪We have completed 84% reclamation of the first island and 75% reclamation for the second island of Centara Three Islands Reclamation project. The construction of a groyne and revetment to mitigate the effects of erosion are ongoing for the first island. Three islands from a lagoon in...

The setting-out survey of breakwater, revetment and quay wall for V. Felidhoo Harbour extension project was completed on March 28,2020. The work focuses on detailed surveys including bathymetry of basin and channel; bathymetry of potential harbor expansion area; elevation profile from harbour area to the vegetation...

3300 tonnes of rock boulders needed for R. Madduvari South Harbour project have been delivered. The rock boulders will be used for breakwater construction. Additional rocks are needed for breakwater profiling to commence. The project, worth over MVR 68.6 million, includes dredging harbour basin and entrance channel,...

The harbor construction work for ‘Design and Build of harbor in N. Miladhoo’ project is moving forward swiftly. Machinery including excavators, diesel tank and welding genset were mobilized to N. Miladhoo on Leema 2, last night. Dredging is scheduled to start on March 28, 2020. (Saturday) A...

The project was inaugurated by Indian High Commisioner to the Maldives H.E Sanjay Sudhir. Dignitaries who graced the occasion included the Minister of National Planning and Infrastructure Mr. Mohamed Aslam, Minister of State for National Planning and Infrastructure Mr. Akram Kamaludheen and Chief Executive Officer of...