Fuvahmulah Ring Road construction is nearing completion, with 87% project progress

Fuvahmulah Ring Road construction is nearing completion, with 87% project progress. The project will result in the development of 20,650 sqm of asphalt road.
Current works include paving a 10, 325 sqm area on both sides of the road, which is a variation approved by the client in February, 2020. The project, which was awarded in March 2019, is expected to be completed by August, 2020.