CEO Adam Azim & Minister of State for National Planning, Housing and Infrastructure Akram Kamaludheen inspects the progress of Ha. Ihavandhoo Harbor Project

CEO Adam Azim & Minister of State for National Planning, Housing and Infrastructure Akram Kamaludheen inspects the progress of Ha. Ihavandhoo Harbor Project.

Work on Ha. Ihavandhoo Harbor is well underway, with overall 26% project progress. The scope of the project includes, dredging and reclamation of 21,295cbm; construction of a 284m breakwater; a 178m revetment; a 95m quay wall; 4,582sqm of paved area and installation of navigation lights.

During this visit Media was also briefed on the latest updates of the project