Work on design and build of Sh. Lhaimagu Harbor Development Project is well underway

Work on design and build of Sh. Lhaimagu Harbor Development Project is well underway, with overall 54% project progress. Installation of precast concrete blocks for quay wall construction is ongoing, with 70% completion.
Sh. Lhaimagu Harbour project consists of; dredging and excavation operations of 31,000cbm; construction of a 350m breakwater; a 276m quay wall; a 500m revetment; installation of 1,380sqm pavement, installation of navigation lights and streetlights. The value of the project is MVR 56.3 million.