Work on design and build of Th. Guraidhoo Harbor Development Project is well underway

Work on design and build of Th. Guraidhoo Harbor Development Project is well underway, with overall 77% project progress. Second shipment of rock boulders have been delivered to the project site on 1 March 2022. Construction of breakwater is ongoing, with 69% completion.
Project works consists of; dredging and excavation operations of 24,485cbm; construction of a 325m breakwater; a 185m quay wall; a 22m revetment and 1,875sqm of paved area. The value of the project is MVR 56.9 million