Work on Design and Build of Sh. Feevah Harbor is well underway, with overall 80% project progress. Installation of precast concrete blocks required for quay wall construction is currently ongoing.
Scope of works for the project include dredging and excavation operations of 55,163cbm; the construction of a 464m quay wall; a 356m breakwater; a 182m revetment, installation of 2,320sqm of paved area, installation of navigation lights and streetlights. The value of the project is 67.6 million.