We have completed harbor basin dredging operations of Aa. Maalhos Harbor.

We have completed harbor basin dredging operations of Aa. Maalhos Harbor. MTCC continues investing on large machineries to avoid explosive blasting of hard strata removal.
Scope of works involve, dredging and excavation operations of 24,335cbm, construction of a 394m quay wall, a 407m breakwater, a 100m revetment, a 56m groyne, installation of 1970sqm harbor pavement, construction of a ramp and installation of harbor lights.
No Comments

Sorry, the comment form is closed at this time.