M. Dhiggaru harbour construction

Status

completed

About This Project

Awarded in 2015, the construction of M. Dhiggarui harbour was signed between MTCC and Ministry of Housing and Infrastructure. The construction work of the 225m long and 91.44m wide harbour commenced in November, 2015 and work was completed in Dec, 2016, within 404 days of commencement of work.

 

The main components of this project included:

Maint. dredging of existing basin 8,949.58cbm

Maint. dredging of existing channel 66.4 Cbm

Dredging of Boat Beaching Area 3,22.57 Cbm

Quaywall:

QW Block Installation 216m

Breakwater & Revetment:

Construction of Breakwater 366.0m

Construction of Revetment 109.00m

Sundries:

Harbour Pavement – Installation of Blocks1,135.00 Sqm

Harbour Lights – Installation of Lights 12 Nos

Beacon Installation 2 Nos

Mooring Block Installation 15 Nos

Project Tpe
Harbour Construction
Location
M. Dhiggaru
Client
Ministry of Housing and Infrastructure
Contract Sign Date
19th May 2015
Project Start Date
1st June 2015
Completion Date
8th August 2017