Land Reclamation and Shore Protection of R. Dhuvaafaru

Status

on-going

About This Project

Land Reclamation and Shore Protection of R. Dhuvaafaru was contracted to MTCC on 10 November 2020 by the Ministry of National Planning, Housing and Infrastructure.

Our dredger Mahaa Jarraafu was mobilized to Dhuvaafaru on 5th March 2021, with which land reclamation works at R. Dhuvaafaru will commence shortly.

Scope of the project includes

  • Dredging & Reclamation of 22.2 hectares (1,089,110cbm)
  • Construction of 423m of rock boulder revetment
  • Construction of 70m breakwater 7

The project cost is 143,111,776.60 MVR.

 

Project Tpe
Dredging and Reclamation
Shore Protection
Location
R. Dhuvaafaru
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
10th November 2020
Project Start Date
5th March 2021