K. Vilimale’ Coastal protection

Status

completed

About This Project

K. Vilimale’ coastal protection project was awarded to MTCC on 1st October 2014, by the Ministry of Environment and Energy. It consisted of dredging of 4,148 cbm harbour basin and new channel, construction of 55m breakwater, construction of 76m concrete quay wall, and navigation lights on the entrance channel. The project was completed on 20th December 2016.

Project Tpe
Shore Protection
Location
K. Vilingili
Client
Ministry of Environment and Energy
Contract Sign Date
1st October 2014
Project Start Date
9th August 2015
Completion Date
20th December 2016