Harbor Redevelopment and Reclamation Project K.Dhoonidhoo project was awarded to MTCC by Ministry of National Planning, Housing and Infrastructure on 05th September 2019

The project was mobilized on 21st September 2020.

Scope of the project includes

  • Dredging and excavation 4.61 acre
  • Reclamation 3.75 acre 
  • Construction of Breakwater 370m 
  • Construction of Revetment 620m
  • Construction of Quay wall 250m
  • Installation of beacons
  • Construction of boat ramp
  • Construction of underwater concrete anchor blocks
  • Installation of harbour lights and 250m pavement  

The MVR 51.4M project is to be completed within 365 days. 

Project Tpe
Dredging and Reclamation
Harbour Redevelopment
Location
K. Dhoonidhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
5th September 2019