Harbour Dredging works of GA. Villingili

Status

on-going

About This Project

Harbour Dredging works of GA. Villingili was handed over to MTCC by Ministry of National Planning, Housing and Infrastructure on 9th September 2020.

Ga. Villingili Harbour dredging works is well underway, with overall 50% project progress.

Scope of the project included

  • Dredging of Existing Harbour Basin & Channel 71,519cbm

The project is valued at MVR9,141,337.00.

Project Tpe
Harbour Construction
Location
G.A. Villingili
Client
Ministry of National Planning, Housing and Infrastructure
Contract Sign Date
9th September 2020