About This Project
Design & Build of Harbour Construction in S. Hulhudhoo was awarded to MTCC by Ministry of National Planning, Housing and Infrastructure on 1st March 2020.
Scope of the project includes
- Dredging and Excavation 88,623Cbm
- Construction of break water 114m
- Construction of revetment 624m
- Construction of quay wall 742m
- Installation of navigation aids and streetlights
- Harbor pavements 2,250sqm
- Construction of a ramp for landing craft
- Construction of 9m x 4m bridgeÂ
The MVRÂ 61.4MÂ project is to be completed within 375 daysÂ