Design & Build of Harbour Construction in S. Hulhudhoo

Status

on-going

About This Project

Design & Build of Harbour Construction in S. Hulhudhoo was awarded to MTCC by Ministry of National Planning, Housing and Infrastructure on 1st March 2020.

Scope of the project includes

  • Dredging and Excavation 88,623Cbm
  • Construction of break water 114m
  • Construction of revetment 624m
  • Construction of quay wall 742m
  • Installation of navigation aids and streetlights
  • Harbor pavements 2,250sqm
  • Construction of a ramp for landing craft
  • Construction of 9m x 4m bridge 

The MVR 61.4M project is to be completed within 375 days 

Project Tpe
Harbour Redevelopment
Location
S. Hulhudhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
1st March 2020