Design and Construction of V. Rakeedhoo Harbour

Status

completed

About This Project

MTCC was awarded the design and construction of V. Rakeedhoo harbour on 1st October 2019. The project was contracted to MTCC by the Ministry of National Planning, Housing and Infrastructure.

The project was mobilized on 08th June 2020.

Work on Design and Build of V. Rakeedhoo Harbour is well underway, with overall 65% project progress. Rock boulders needed for the project have been unloaded to the project site on 29 December 2020.

Scope of the project includes
  • Dredging operations of 5,554cbm for new harbor basin
  • Dredging operations of 100cbm for existing channel
  • Construction of a 156m breakwater
  • Construction of a 74m revetment
  • Installation of 594sqm of paved area.
The project was completed on 6th April 2021.
The value of the project is MVR 18.5 million.
Project Tpe
Harbour Construction
Location
V. Rakeedhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
1st October 2019
Project Start Date
8th June 2020
Completion Date
5th April 2021