Construction of major roads at B. Eydhafushi

Status

on-going

About This Project

The construction and development of  main roads at B. Eydhafushi was signed between the Permanent Secretary at the Ministry of Planning and Infrastructure, Zeeniya Ahmed Hameed and the COO of MTCC Shahid Hussain Moosa, on April 1st, 2019.

 

This project includes:

17785 sqm road

Installation of storm water management system

Supply and installation of 172 LED street lights

Construction of speed breakers and road markings on 8426M

 

The MVR 38,338,277.91 project is estimated to be completed within 240 days. 

Project Tpe
Road Construction
Location
B. Eydhafushi
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
1st April 2019