Construction of Lh. Hinnavaru Harbour Extension

Status

on-going

About This Project

Construction of Lh. Hinnavaru Harbour Extension was handed over to MTCC by Ministry of National Planning, Housing and Infrastructure on 10th November 2020. The contract of the project was signed by CEO of MTCC Adam Azim and Director General of Planning Ministry, Shana Farooq.

The scope of the project includes

  • Dredging & Excavation of 32,585.38cbm
  • Construction of 653.2m of quay wall
  • Construction of 124m of breakwater
  • Construction of 90m groyne
  • Construction of 31.88m revetment
  • Construction of 3,454.31sqm of harbour pavement

The value of the project is MVR 99.52 million. The project is to be completed within 350 days.

Project Tpe
Harbour Redevelopment
Location
Lh. Hinnavaru
Client
Ministry of National Planning Housing and Infrastructure
Contract Sign Date
10th November 2020
Project Start Date
13th March 2021