Construction of B. Fehendhoo Harbour

Status

on-going

About This Project

The construction of of B. Fehendhoo harbour was awarded to MTCC on 2nd July 2019 by  the Ministry of National Planning and Infrastructure.

Work on Design and Build of B. Fehendhoo Harbour is well underway, with overall 75% project progress. We have completed quay wall construction works.
Scope of this project includes
  • Dredging and excavation of 43500cbm
  • Development of 130M breakwater
  • Development of 282M revetment
  • Development of 214M quay wall
  • Construction of a ramp
  • Interlocking pavement
  • Installation of mooring blocks, navigational masts and harbor lights

The MVR 49,664,831.39 project is to be completed within 365 days. 

 

 

Project Tpe
Harbour Construction
Location
B. Fehendhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
2nd July 2019
Project Start Date
10th November 2019