A.Dh. Fenfushi Break Water Construction

Status

completed

About This Project

The A. Dh. Fenfushi break water consstsruction project was awarded to MTCC in 2015 by  the Ministry of Housing and Infrastructure. The project was completed during 2017.

 

The project included:

Dredging and excavation (basin & channel) 33,262 m3

Breakwaters 385 m

Project Tpe
Harbour Construction
Location
A.Dh. Fenfushi
Client
Ministry of Housing and Infrastructure
Contract Sign Date
12th April 2015
Project Start Date
14th November 2015
Completion Date
18th April 2017