Work on R. Fainu Shore Protection Project is well underway

Work on R. Fainu Shore Protection Project is well underway, with overall 63% project progress. We have commenced construction of revetment for shore protection on 1st November 2021.
Scope of works for the project include, sand backfilling of 8100cbm and construction of a 250m geobag revetment. The value of the project is MVR 8.96 million.