22 Aug Work on F. Magoodhoo Land Reclamation and Shore Protection Project is well underway
Work on F. Magoodhoo Land Reclamation and Shore Protection Project is well underway, with overall 53% project progress. Rock boulder shipments have been delivered to the site. Rock boulder revetment work is currently ongoing.
Scope of works include, 17 hectares island reclamation operations, 30.8 hectares airport reclamation operations, 1,948m rock boulder revetment, 1,665m geo bag revetment, 90m groyne. The value of the project is MVR 232.26 million.